Tract
Map Improvement Plan Permit
USD's required
permit process for tract projects:
- Submit complete plans for review. USD will only review complete
plan submittals (see below)
- During the initial review, USD will estimate plan check fees
based on the total estimated sewer construction cost and will
generate a fee schedule
- Plan review fees are due after the first review, upon pick-up
of plan review comments
- Each plan review submittal can take up to 10 business days to
complete. Submittals are reviewed on a first-come, first-served
basis
- If no major changes are required, USD will approve the drawings
for construction. This approval is not a permit
for construction. If changes are required, drawings must be revised
and resubmitted for review until USD approval is obtained
- Submit two copies of plans signed by the city of jurisdiction,
and Filed Final Tract Map to USD
- USD will calculate fees for: Permit, inspection, any capacity/connection,
and any work orders. Proof of bonding may be required
- Upon payment of all fees and submittal of signed plans and Final
Tract Map, a sewer permit may be obtained by the party contracted
to do the underground construction
- All contractors wishing to obtain sewer construction permits
for work in the Union Sanitary district must present evidence
of current California Contractors license, Workers Compensation
insurance, and General Liability insurance with Union Sanitary
District as an additional insured
- Upon payment of all fees and submittal of signed Plans and final
Tract Map, a sewer permit may be obtained by the party contracted
to do the underground construction
- Three sets of cut sheets must be submitted to USD for review,
which are returned within 24 hours
- Call your USD inspector 24 hours before beginning sewer construction
to schedule inspection
Permits for lateral connections
can be issued only after the mains have been tested, approved and
accepted by USD. The developer or contractor will provide the building
permits of the lots that will connect. A fee schedule for each lateral
will be generated as per the fee detail below:
| |
Permit Fee |
$50.00 |
| |
Inspection Fee (Property Line to Building) |
$150.00 |
| |
Capacity Fee |
$4,844.73 |
| |
Sub-total |
$5,044.73 |
| |
|
|
| |
Deposit (Refundable upon final acceptance) |
$500.00 |
| |
Total Fees and Deposit: |
$5,544.73 |
*Permit holder deposit
will be $500.00 per lot, up to a maximum of $2,500 (5 lots),
OR
Contractor will deposit
$5,000 cash, check or Dertificate of Deposit (CD)
USD's
requirements for complete plan submittal:
See Tract
Map Improvement Plan Submittal Requirements for
additional details
- Request
for Plan Check form
- Two copies of the civil site plan
- Two copies of Tract map for review
- One copy of any USD Grant of Easement documents
- One copy of CC & R's for review (condominiums only)
- Digital Submittal